Most builders set retainage at 10% because that's what the last contract said.
A lot of states cap it lower than that and set the clock for releasing it after substantial completion.
Write in a percentage your state doesn't allow and the clause doesn't hold.
1
1
35
Impact fees are assessed the day the permit issues, per unit.
Sit in review while the schedule goes up and you pay the new one.
What freezes it is a vesting map or a development agreement, and you have to ask before you file.
3
2
108
Two houses, same 3,000 feet. One has 1,000 of it below grade.
The appraiser doesn't call that one 3,000. The below-grade part sits on its own line and the comps discount it.
Cheaper per foot to build, and it reads as less house at the refi.
1
1
48
The appraisal is good 90 to 120 days. The DSCR cash-out wants six months of seasoning.
Order the appraisal early and it expires before you're eligible.
The fix is a recert, and a recert can come back lower.
Count backward from the seasoning date.
Your owner's title policy excepts anything an accurate survey would show.
The neighbor's drive over your corner. A utility line across the back.
Not covered unless you order the survey and have the exception deleted.
You find out the day you go to build.
Electric and gas go in the tenant's name. In a lot of cities water and sewer can't.
The account stays with the house. An unpaid balance rides on the property long after that tenant is gone.
You find out at the next closing, when title makes you clear it.
2
4
91
An $80,000 house can cost $140,000 to rebuild.
The policy prices off the $140,000.
Most people budget insurance as a percentage of purchase price and find that out at renewal.
Quote it during the inspection period, off the rebuild number.
1
2
45
A 3BR that becomes a 4BR usually picks up more rent than the room costs, because the payment standard moves per bedroom.
Two things kill it. Egress on the window, and the 4BR utility allowance comes straight back out of your number.
Most price only the framing.
1
2
44
Three weeks of hard money carry on a $250,000 loan is about $2,300.
That is what an unset electric meter costs while you wait on the utility.
The electrician can file the service application the day he quotes it. Most file it the day they start.
Two numbers on the same house.
A contractor walks it and says about $90,000.
A dated bid on letterhead with the scope attached says $106,000.
The lender funds off the second one. So does the seller when you ask for a credit.