ALT El-Fasher | 27 August 2025 Ongoing berm construction surrounding the city Copyright: Satellite Imagery 06 July 2025, 28 July 2025, 27 August 2025 © 2025 Maxar Technologies; Map Data:© 2025 OpenStreetMap Contributors; Analysis conducted by Yale HRL Map shows the city of El-Fasher with two semi-circle segments with different colors surrounding at least 2/3 of a ring around El-Fasher. Analysis of several satellite images from different sensors shows a visible berm being constructed around the city of El-Fasher. The construction began with the first berm segment (blue line) which, from its eastern end, connects from the wadi bisecting El-Fasher, then follows westward intersecting the northern access route out of El-Fasher, and ends at the Kutum-to-El-Fasher road. This 7 km berm segment was completed between 05 May and 12 July 2025.